CODES AND STANDARDS
The fryer must be installed in accordance with:
In the United States:
State and local codes, or in the absence of local codes, with:
National Fuel Gas Code, ANSI-Z223.1/NFPA #54 (latest edition).
In Canada:
Local codes
CAN/CSA-B149.1 Natural Gas and Propane Code (latest edition).
NATURAL GAS CONNECTIONS
NOTICE All gas supply connections and any pipe joint compound must be resistant to the action of
propane gases.
Codes require that a gas shutof
f valve be installed in the gas line ahead of the fryer.
The NATURAL GAS supply line must be at least the equivalent of 1/2” (12.7 mm) iron pipe for single
units and 1-1/4” (31.75 mm) dual units. If using the optional quick-disconnect flex hose, 3/4” (19
mm) iron pipe for single units and 1-1/4” (31.75 cm) iron pipe for dual units.
Make sure the pipes are clean and free of obstructions, dirt, and piping compound. A dual unit requires
one or two connections of appropriate size for the gas requirement.
WARNING Prior to lighting, check all joints in the gas supply line for leaks.
Use soap and water solution. Do not use an open flame.
After piping has been checked for leaks, fully purge gas pipes to remove air.
NOTICE Inspect hose(s) frequently. Replace with original manufacturer’s parts only.
CROWN VERITY INC., 37 ADAMS BLVD., BRANTFORD, ON. CAN. N3S 7V8
TEL: (519) 751-1800 FAX: (519) 751-1802
www.crownverity.com
Email: info@crownverity.com
Page view 5
1 2 3 4 5 6 7 8 9 10 11 ... 15 16

Comments to this Manuals

No comments